Drawings
Map1 Geographical context 25k @A3
Map2 Site Location Substation 10k OS @A3
Map3 Site Location Substation 2.5k OS @A3_Part1
Map3 Site Location Substation 2.5k OS @A3_Part2
Map4 Site Location Substation OS Historic 6inch @A3
Map5 Field Numbering with Substation Location 10k @A3
301 Permitted Sightline & Entrance Details
302 Shared Solar Farm and Substation Access Track Plan_Part1
302 Shared Solar Farm and Substation Access Track Plan_Part2
302 Shared Solar Farm and Substation Access Track Plan_Part3
302 Shared Solar Farm and Substation Access Track Plan_Part4
303 Track Details for Substation and Solar Farm Access
304 Truck Access - Permitted Site Entrance_Part1
304 Truck Access - Permitted Site Entrance_Part2
401 Layout Masterplan Substation
404 Site Cross Section Sheet 1
404 Site Cross Section Sheet 2
405 Substation Compound - Layout
406 Substation Compound - Elevations
407 Overhead Line Interface Tower Detail
408 EirGrid Building Plan & Elevations
409 IPP Control Building Plan & Elevations Sheet 1
409 IPP Control Building Plan & Elevations Sheet 2
411 Substation Compound Entrance Gate Detail
412 Concrete Post and Rail Fence Detail
414 Typical Transformer Bund & Plinth Details
415 Foul Holding Tank Detail (Typical)
416 Typical Lightning Mast Details
417 Typical Harmonic Filter Detail
418 Overhead Line Interface Elevations
502 Permitted Battery Container
503 Typical Fence and CCTV details
505 Battery Container Compound
507 Temporary Construction Compound
509 Permitted Span Bridge Detail
2022-24 BIOXL-01.2 Survey Summerhill Rev1 2D
200931-a Clonymeath S182-P01-Draft Drainage Layout-2023.11.02